Miller Street Power & Paving Upgrades
Council, in partnership with Essential Energy, advises the community that electrical and paving works on Miller Street are now underway and progressing along the project area.
Scroll to the bottom of the page to view photos of each project section, and read the latest updates below.
Section 1 – Fronting Mitre 10:
- Section 1 is now fully complete.
Section 2 – Fronting the former SPAR building:
- Section 2 is now fully complete.
Section 3 – Former SPAR building to Gil Library Hub Plaza:
-
Section 3 is now fully complete.
Section 4 - GIL Library Hub Plaza to Joblink Plus:
Section 5 - JobLink Plus to Sheer Style Hair Design:
- Council advises that works on Section 5 have been adjusted due to unforeseen circumstances identified during construction works.
- Following the completion of Section 4, contractors moved to Section 8, from Noonan Memorial Park through to Thompsons Flooring.
- Temporary fencing remains in place in front of Joblink Plus until works in this area recommence, with a temporary footpath bypass in place for pedestrians, including ramp access.
- Further updates will be provided as works progress.
- New seating installation has also commenced as of 28 September.
Section 6 - Thompson's Flooring to Tingles Massage & Beauty:
- Section 6 is now fully complete, including re concreting of the driveway adjacent to Tingles.
Section 7 - Gil Ag & Auto to Windmill Crafts:
- Mobil exit driveway (adjacent to Gil Ag & Auto) concreting is now complete.
- Essential Energy trench excavation & repaving works from Gil Ag & Auto, up to Windmill Crafts will commence week starting 23/11/26.
Section 8 - Noonan Memorial Park to Thompson's Flooring:
- Section 8 is now fully complete.
Section 9 - The Old Bank to Gil Ag & Auto:
- Works in this section are set to commence following the completion of section 10.
Section 10 - Rohr's Trading to The Old Bank:
- Repaving works have commenced from Rohr's end as of Friday, 13 November.
- Footpath damage repair and upgrade works around the old Bank building will be completed week ending 27/11/26.
___
To avoid disrupting shopfronts during their peak festival trading season, works will not proceed north past Windmill Crafts during November and December.
Trenching on the western side will be less extensive, with Essential Energy works limited to the area between Gil Ag & Auto and Windmill Crafts.
The project will involve:
- Relocating overhead electrical services underground.
- Renewing approximately 670 metres of footpath paving along Miller Street.
- Installation of new street seating along Miller Street.
- Works being staged and completed progressively to minimise disruption. Access to businesses and pedestrians will be maintained wherever possible.
Ongoing project updates are also available via Council's Facebook page.
| How long will this project go for? |
This project is scheduled to run for approximately three months
across two phases:
Phase 1: 17 August 2026 to 19 September 2026.
Phase 2: Commenced 28 September 2026.
Due to unforseen circumstances during works, expected project
completion is January 2027 (weather permitting).
|
Will works affect my business during peak
Christmas trading? |
Northbound works will pause at Windmill Crafts for Christmas, with the area
to be tidied by 16 December 2026.
No further works to the north of Windmill Crafts will take place until work
resumes on 4 January 2027. Instead, repaving is to be completed
back towards Rohrs.
|
|
Will my business have to close?
|
Access to businesses will be maintained wherever possible, and should not require any closures.
Council will communicate directly with impacted businesses to provide
updates as work progresses.
|
|
Will I be able to access shops on Miller St?
|
Both pedestrian and business access will remain open wherever possible.
Please use extra caution when walking near construction zones.
|
|
What will happen to car parking on Miller St?
|
A maximum of five parking spaces will be temporarily closed at any
one time as work progresses down the street.
|
| Will trenching continue through the full length of the footpath on both sides of Miller Street, and will there be trenching in front of my business? |
Eastern Side (Library Plaza): Trenching runs from Bridge St to the War Memorial, followed by repaving.
Western Side (Cooee Statue): Trenching is limited to the section between
Gil AG & Auto and Windmill Crafts. Repaving, however, will occur along
the full length from Bridge St to Rhors Timber and Hardware.
|
| What is the expected outcome of this project? |
Underground power cables - replacing overhanging power cables
on Miller St awnings to improve safety compliance standards.
Renewed footpath featuring brand-new pavers along
approximately 670 meters of Miller Street.
|
| Will my building be without power? |
Current works involve installing underground conduits, with
Essential Energy to install and energise power cables at a later stage.
Any outages are planned to occur out of business hours, with direct
engagement to be conducted with affected businesses.
|
See below for project photo updates;
Section 1 - Fronting Mitre 10
Section 2 - Fronting the former SPAR building
Section 3 - Former SPAR building to Gil Library Hub Plaza
Section 4 - GIL Library Hub Plaza to Joblink Plus
Section 5 - JobLink Plus to Sheer Style Hair Design
Works on Section 5 of the Miller Street paving upgrades, from JobLink Plus through to Sheer Style Hair Design, have been adjusted due to unforeseen circumstances identified during construction.
Following the completion of repaving works in front of the GIL Library Hub, contractors have moved to Section 8, from Noonan Memorial Park through to Thompsons Flooring.
Temporary fencing remains in place in front of Joblink Plus, with a temporary footpath bypass available for pedestrians.
Section 6 - Thompson's Flooring to Tingles Massage & Beauty
Section 7 - Gil Ag & Auto to Windmill Crafts
Section 8 - Noonan Memorial Park to Thompson's Flooring
Section 10 - Rohr's Trading to The Old Bank